Westwood Neighborhood to receive an update starting in July
As part of our ongoing efforts to address our road conditions here in Napa, we are ramping up to begin work in the Westwood Neighborhood soon. This is a multi-phase project that will start with asphalt overlays, sidewalk repair, and curb, gutter and ramp replacements on Kilburn Avenue, Bryan Avenue, Chelsea Avenue from Kilburn Avenue to 1st Street, Bancroft Court and Bremen Court. We anticipate to start construction in July of this year, and expect this phase of the project to last about 3 months.
To keep the neighborhood informed, we will be hosting a community meeting about the project on April 5th. Notices have been sent out to residents in the area already!
Meeting Details
Westwood Neighborhood Street Rehabilitation Phase 1
Date and Time: April 5th, 2018 from 6:00 pm-8:00pm
Where: Multi-Purpose Room/Cafeteria at the Napa Valley Language Academy, 2700 Kilburn Ave., Napa