Resurfacing of a number of residential streets will take place the week of October 6. The Annual Street Resurfacing project consists of asphalt-rubber chip seal application, slurry seal application, crack filling and restriping. The asphalt-rubber chip seal application will commence according to the schedule below. The slurry seal application will begin approximately one week after the chip seal. 

Click on "Read More" for project details and a list of the streets where this work will take place.

The asphalt-rubber chip seal consists of a liquid asphalt-rubber that is sprayed onto the street followed immediately by small aggregate rock called “chip” being placed on the asphalt-rubber and then rolled into the liquid.  The street is then swept several times to remove any loose chips.  The liquid asphalt rubber is approximately 20% rubber by weight.  For this project approximately 10,500 used tires will be recycled and used for this resurfacing treatment.  Approximately one week after the asphalt-rubber chip seal has been placed, a slurry seal will then be applied.  The slurry seal covers the rough finish left by the chip seal and provides additional protection for the street.  The combination of these two applications provides for a strong durable surface, improves skid resistance, and extends the life of the street.  Please note the asphalt-rubber chip seal surface is very rough but will be smoothed once the slurry seal is applied.

To apply the asphalt-rubber chip seal, the roads listed above will be posted “No Parking” on the dates indicated between the hours of 7am – 5pm.  Please be aware that cars parked in areas posted with “No Parking” signs will be towed at the owners expense.  All residents of these streets will have been mailed notification of this work and will be given additional information.  Emergency access will be maintained at all times.

The work will be performed by International Surfacing Systems of Modesto, CA.  The Asphalt-Rubber Chip Seal application schedule and streets affected are as follows:

Monday, October 6, 2008       
CHABLIS DRIVE from GRAPE VINE DRIVE to VINE HILL DRIVE
CHABLIS COURT from CHABLIS DRIVE the end
MALAGA COURT from   S WINE COUNTRY AVE to the south end
LINDA MESA WY  from  SCENIC DR  to the end
ELLEN COURT  from  ELLEN WAY to the north end
COVEY CT from DOUGLAS AVE to the end
DEERFIED DR from SCENIC DR to PARTRICK RD
CENTURY DR from SCENIC DR to the end
ANTIA CT from WESTVIEW DR to the END
BUCKEYE CT from BANBURY CT to the end
KENSINGTON CT from KENSINGTON CIR to the west end
AUSTIN WY from SCENIC DR to BROWNS VALLEY RD
       
Tuesday, October 7, 2008       
GRAPE VINE DR from  S WINE COUNTRY AVE to VINE HILL DRIVE
FLORA STREET from CHABLIS DRIVE to MALAGA WAY
MADEIRA COURT from CHABLIS DRIVE to the end
SCENIC DR from BROWNS VALLEY RD to DOUGLAS AVE
SCENIC DR from WESTVIEW DR to AUSTIN WAY
MASON ST from LINDA MESA WY to SCENIC DR
DEERFIED CT from DEERFIELD DR to the end
CENTURY CT from CENTURY DR to the end
DOUGLAS AVE from SCENIC DR to COVEY CT
ELLEN WY from DOUGLAS AVE to the end
CRAIGIE CT from CENTURY DR to the end
BANDURY CT from SCENIC DR to the end       
       
Wednesday, October 8, 2008       
SCENIC DR from DOUGLAS AVE to WESTVIEW DR
SCENIC DR from AUSTIN WAY to LARKIN WAY
AUSTIN WY from CARMEL DR to SCENIC DR
WESTVIEW DR from SCENIC DR to BROWNS VALLEY RD
LATHROP STREET from NORTON ST to CARRIAGE PL
JACOB COURT from CARRIAGE PL to the west end
KENSINGTON CIR from SCENIC DR to AUSTIN WY
  
Thursday, October 9, 2008       
SUNVIEW DR from WESTVIEW DR to WESTVIEW DR
PINEWOOD DR from SKYCREST WAY to SCENIC DR
WOODLAWN DR from SCENIC DR to BROWNS VALLEY RD
EUGENE COURT from AUSTIN WAY to the west end
BEECHAM STREET from WINSOR ST to PUEBLO AVE
BEECHAM  COURT from BEECHAM ST to the east end
COOLIDGE DRIVE from PUEBLO AVE to CARRIAGE PL
CARRIAGE PLACE from CENTRAL AVE to the west end
JOSEPH COURT  from the west end to the east end
LATHROP COURT from CARRIAGE PL to the east end
NORTON STREET from LATHROP ST  to GRANT ST
GRANT STREET from NORTON ST  to ALICE ST
ALICE STREET from LATHROP ST to CENTRAL AVE.

PLEASE NOTE that this schedule could change due to unexpected weather or construction problems, resulting in some delays or re-scheduling of a street to a completely different day.  If a street is not resurfaced on its originally scheduled day, the street will be moved to the end of the project schedule.  This is done so that the next day’s schedule is maintained and proper notification can be made to affected residents.  The City will try to avoid such inconveniences if at all possible.  In all cases, residents will be notified of rescheduled dates 48 hours in advance through notification by the contractor and the presence of blockades the day before resurfacing operations begin.

The City of Napa appreciates your patience and cooperation during construction.  If you have any questions or need additional information, please contact Mike Socorro of the Public Works Department at 257-9520, ext. 7305.