New Development and Construction
Please note: If you simply need to get an existing water service turned on and establish the account in your name, please call the Finance Department at 707-257-9508, Email the Finance Department, or visit the Finance windows at:
City Hall
955 School Street
Napa, CA 94559
New Water Service Connection Procedures
Procedures for establishing new connections to the City of Napa water system vary depending on site location and project size:
Inside City Limits
For an existing house, a vacant lot, or to separate services for a duplex or triplex, Email the Utilities Development Team, call 707-257-9521, or visit the Utilities Department at 1700 Second Street. You will be advised regarding service eligibility, water capacity fees, service pipe installation, meter sets, and scheduling. Prior to scheduling the hot-tap and service installation, you must pay all Required Water Service Fees (PDF).
Outside City Limits
Please note: Outside Water Service Application procedures are subject to City Charter Section 180, Policy Resolution No. 7, and Government Code 56133.
For most sites outside the City limits, you must pay a $617 filing fee and complete an Outside Water Service Application (PDF) to determine eligibility. If approved, you must complete the conditions of the application and pay all Required Water Service Fees (PDF) prior to installation. Call the Engineering Assistant at 707-257-9521, Email the Engineering Assistant, or visit the 1700 Second Street headquarters for more details.
These two areas do not require completion of an Outside Water Service Application:
- Congress Valley Water District - Leave a message at 707-256-0344 or Email the District’s Secretary to initiate the application process.
- Silverado Resort Area - Contact the Engineering Assistant as previously listed.
Large Development
For subdivisions, hotels, or other large projects requiring new development of the water distribution system, call the Water Engineer at 707-257-9266, Email the Engineer, or visit the 1700 Second Street headquarters.
Standard Requirements/New Development
- All new services require installation of a backflow prevention device.
- Contractors should be familiar with the provisions and requirements contained in the Water Division Standard Specifications.
- Prior to occupancy, new development must meet its water demand mitigation (offset) requirements as specified by the Water Division.
- New development projects may be subject to High Performance Building Regulations and/or the Water Efficient Landscape Ordinance (WELO).
Construction Water/Hydrant Meters
If temporary water service is needed for construction purposes, complete a Temporary Hydrant Meter Application. After review of application a temporary hydrant meter permit may be issued.
Helpful Online Forms:
- Accessory Dwelling Unit (ADU) Pre-Application
Use this form to request water service information before submitting to the Building Division for an Accessory Dwelling Unit (ADU) building permit. - Fixture Count Worksheet for ADU
Use this spreadsheet to calculate the water fixture demands. A water service and meter sizing table can be found at the following link, Water Service Sizing table, to determine whether the existing water service size will meet all proposed water demands with the ADU. For questions or assistance completing these forms please contact the Water Division (707) 257-9521 or Email the Utilities Development Team. - Utility/Facility Map Request
Use this form to request utility information from the City of Napa. - PG&E Self-Generation Incentive Program
Use this form to request a Water Service Access letter from the City for your PG&E SGIP application. - Water Service "Will Serve" Letter Request
Use this form to request "Will Serve" letters. This form should only be used for parcels inside Napa City Limits requesting water service from the City of Napa. Please allow 3-5 business days for a response.