Paving will start up in the Westwood Neighborhood starting tomorrow, Friday, January 18, and continue per the schedule below, through Thursday, January 24. This is part of yet another phase in a series of much-needed improvements to our Westwood Neighborhood!
Friday 1/18/19 – Kilburn from Arrowwood to Avon
• Edge grinding 6 ft. next to curb. Starting on south side then moving to the north side.
• Minimum one lane traffic with flaggers at all times
• No Parking will be allowed on Kilburn
• Will only allow drop-off/pickup at school entrance
Monday 1/21/18 (SCHOOL HOLIDAY) – Kilburn from Avon to Bremen
• Asphalt paving on Kilburn
• Multiple passes to pave each lane
• Minimum one lane traffic with flaggers at all times
• No Parking will be allowed on Kilburn
• Will only allow drop-off/pickup at school entrance
Tues 1/22, Wed 1/23, Thur 1/24 - Bryan from Laurel to Kilburn and Kilburn from Arrowwood to Bremen
• Bryan = grinding/paving from Laurel to Kilburn
• Kilburn – paving from Arrowwood to Bremen
• Multiple passes to pave each lane
• Minimum one lane traffic with flaggers at all times
• No Parking will be allowed in work zones